So it was a pleasure to be building a timber deck for my customer Pam in Fremantle, with her friend Anna as a TA assisting me. I take my hat off to Anna for working so hard despite the heat and for being such a quick learner. Together we have been a good team and progress had motored along. Such an interesting old house. In a former life it was a bakery, now undergoing a serious renovation. It is always so interesting to me to work on old places. They just ooze with character.
In case deck building is something you're about to tackle and is not something you've done before, I hope this post may provide you with some ideas and tips for how to do it and make a really good job of it too...
Planning the job.
Once my customers had given me the dimensions and details of the position and height of the deck, my task was to first draw it up. The scale drawing process brings together the planing the construction, the dimensions and types of materials to be used, and the calculating of the quantities. Within the Building Code of Australia we have "span tables" which provide guidance and minimum standards for the selection of materials and the specification of acceptable maximum spans for bearers and joists for decking. This deck was to be at floor level (about 450mm above the planned ground level) so there was no balustrading to consider.
Doing a scale drawing enabled the specs and quantities to be calculated. |
With the calculations and the scale drawing completed, I emailed off the drawing to my customers for approval. We met again to discuss the details further and a starting time and they ordered in the materials based on the quantities lists I had provided. After some discussion, CCA treated pine was chosen as the timber to use. All metal fixings (nails, screws, bolts, stirrups etc) would be hot dipped galvanised.
Setting out the job on site.
When I returned to commence the job, I found that the old concrete verandah had been removed, the soil level had been lowered, and Anna had used the drawing to pre-dig the holes for the metal stirrups which would be used in the place of timber stumps - to support the bearers. The timber was on site as with as most of the other materials that we would need. Everything was ready to go. Working backwards from the intended height of the decking surface, we determined the required level of the top of the bearers. We used my el-cheapo laser level to establish a reference line, and knew what height below that reference line the tops of the bearers had to be established. String lines helped to define the outer limits of the deck based on the required dimensions. The deck was to be in an L-shape, with the long leg being almost 10m ( 32.5 ft) by 2.1m (7 ft) wide. The short leg would be 7.5m long (24.5 ft) by 3.0m (10 ft) wide, meaning the 3.0m wide section extended a further 5.4m (17.5 ft) beyond the 2.1m section. This 10m long x 2.1m section was under an existing verandah. The edge of the deckline was to be directly below the verandah plate above it. This deck line was determined with the use of plumb lines from the top plate. The total area of decking would be about 37m2 (400 ft2).
Laying out the bearers and stumps.
There are a number of ways to do this, but my preferred method is to make up the bearers full length, attach the metal stumps (stirrups), suspend the bearers levelled and in the correct positions, and pour the concrete around the stirrups. These days, it is common for bearers to be made up from two narrow sticks nailed and bolted together as a pair. In this way we made up the two bearers that were 10m long each, and the remaining 3 bearers which were 3m long each. The joints in the 10m bearers were staggered, mitred, and always over a stirrup. The bearers in this way were made from pairs of 120mm x 45mm CCA treated pine sticks.
The two 10m long bearers, propped up and in position, with concreting under way. Temporary prop holding up the verandah until the new verandah posts go in. |
The placement of frequent temporary supports, (made up of bricks, blocks, pieces of timber and fine-tuned with assorted packers) enabled the bearers with the stirrups already bolted on to be suspended over the holes ready for concreting. The laser level was used to ensure the bearers at each support and stirrup were leveled at the required height. When the bearers were all set up ready, the concrete was mixed and poured around each of the 23 metal stirrups, and left for a couple of days to dry.
Fixing the joists.
Before the joists were fixed to the bearers, the aluminium flashing was rolled out along the tops of the bearers. This flashing prevents the ingress of moisture between the pairs of timber making up the composite bearers, and thus greatly improves the durability of the bearers.
The joist positions were set out over the bearers, at 365mm centres. This is a little closer than the original plan, but putting an extra joist in the span will improve the decking by marginally reducing the spring in the decking. I am happy to be accused of over-engineering. String lines were used to ensure the joists were nailed in straight lines, and each joist was skew nailed from each side into the bearer below at each junction. Lots of 4 inch galvanised nails, pounded in by hand using my trusty old Cheney hammer.
While the concrete was curing, I was still able to cut the joists to length ready for fixing down the next day. The flashing has yet to be rolled out along the tops of the bearers. |
The joints in the joists were always staggered, mitred and centred over the bearers. The bearers and joists were always left "over-long", to be cut to final length later.
The long run of the decking structure, with most of the joists now cut to length, determined via stringline. |
The original verandah posts had to be removed in order to undertake this work, before the bearers could be positioned in place. Amazingly enough, the old verandah top plate was full length - 10m (over 32 feet) which is a long 8"x2" of jarrah! You can't get them like that any more... Anyway, in order to do this and provide the support, I first had to pick up the plate half way along it's length. The picture above shows how I did this. Once the temporary support was in place, the original posts were removed. The bearer/stump positions had been planned so that the new verandah posts would each be over a stump.
The nailing down of the joists is the part of the job I always find very satisfying. You can really see the progress unfolding as you go.
Tips for fixing down the decking.
The decking boards on a completed deck are what is seen the most, not the structure below it. It is therefore very important that the boards are nailed down straight, with regularly placed fixings, and with nothing that jarrs the eye. Here are a few tricks to doing it right:
1. Work from string lines. With a stingline taut between one end of the joist to the other, the line of nails should be beautifully in line. It will look really good.
Nailing down in progress. Sticks in the foreground under the stringlines and ready to be used. |
String line used with consistent nail placement pattern. Note the remaining spacer - the others have been removed. Note also the tidy butt joint under the stringline. |
Deformed shank (spiral) galvanised decking nails, skewed. Doubly good holding power. |
A few spacers shown in place here. Short board in foreground yet to be cut to length |
Looking good. New verandah posts in place. Full length reference lines used to ensure lines remain straight. |
7. Finish the edge cleanly with a fascia.
Having a defined edge by the use of a fascia board makes a huge difference to the look and the finish of the deck. Daggy ends of a deck are not a good look. Housing them within a nice clean border makes for a much better product.
Fascia board made with use of a decking board. In this case the brick paving will be built up flush to the top of the decking. That's the retaining wall partly under construction. |
9. Take pride in what you do, and be your own harshest critic.
It's never OK to say settle for second best and say "that'll do". With power tools it's easy to make a mess of cuts. Too much power and not enough control makes for a lack of accuracy. However with hand tools it's all up to you how much attention to detail that you maintain and how accurate your cuts and hammering will be. That's one of the great things about using hand tools.
Worried that your skills are not up to it? Keep your tools sharp and your hand skills will improve quickly while you use them on the job. Don't settle for second best. If your cut isn't square, do it again.
Nice job, eh? And it is really so easy to do... |
So there you go... the story of a deck. Thanks again to my ever reliable off-sider on this job, Anna, for being so quick to learn and for putting up with my demanding attention to detail.
Now Pam, it's time for you to enjoy that sherry on your new deck...